interior view of dining area of wellness center building with black tables and chairs and glass curtain wall

An R&D Campus Built to Develop Life-Changing Treatments

Aperture Del Mar Phase 2 | San Diego, California

DPR served as the core-and-shell builder for two 140,000-sq.-ft. four-story office buildings (B3 and B4), as part of the larger five-building Aperture Del Mar development. The project will serve as the new corporate headquarters for Neurocrine Biosciences, one of San Diego’s largest life science companies. Housing primarily office and R&D lab space, the new campus will be dedicated to discovering and developing life-changing treatments for patients with debilitating neurological, neuroendocrine, and neuropsychiatric disorders. Other scopes of work include 35,000-sq.-ft. basements for each building, site work, a new loading dock, and a 13,000-sq.-ft. fitness center.

About the

Project

Located in Del Mar, within the nation’s third-largest life sciences cluster, the new campus will provide a fully amenitized innovation and research environment. Purpose-built for Neurocrine, Aperture was designed around flexibility and scalability; at full build-out, the campus will include five buildings, a standalone parking structure, and an outdoor amenity space with an event lawn, walking paths, and an amphitheater. In addition to the two Phase 1 buildings, Phase 2 will bring the workspace total to 535,000 square feet at full build-out.

Project

Innovations

Laser-Scanning for Quality Control

Each floor's composite deck had thousands of penetrations for pipe sleeves and hangers, which required exact placement to avoid rework. DPR's VDC team laser-scanned each deck before the Self-Perform Concrete crew poured. From here, strategic partner VConstruct immediately back-checked all scans against the project BIM model for quality control. Once the deck cured, the VDC team went back and laser-scanned again, ensuring all floors met tolerance for flatness.

Preventing Supply Chain-related Delays

Due to supply shortages of power transformers and switchgear, lead times from San Diego Gas & Electric (SDG&E) were unknown—creating potential for delays to the project. In response, the project team leveraged its relationships and worked closely with their planner, SDG&E, Gemdale, and trade partners to strategize procurement and make-ready work. The team set and energized all transformers and all plant and equipment before switchgear was set inside the building, avoiding impacts to the schedule.

Phased Turnover of Active Campus

To maintain tenant access to Buildings 1 and 2 during construction of Buildings 3 and 4, the core-and-shell team worked closely with facilities, trade partners, self-perform crews, and the TI project team to coordinate a smoother phasing process. This helped prevent disruptions to occupied spaces as well as create efficiencies for the incoming TI work. Solutions included building a pedestrian bridge from the parking garage to Buildings 1 and 2, allowing office users to safely traverse through the active construction zone.

exterior view of concrete structural frame of five-story building 4
interior view electrical room where two electricians are installing switchgear
a DPR project team member shows two trade partner foremen a dig board outside of the project trailer
Project

Innovations

exterior view of concrete structural frame of five-story building 4

Laser-Scanning for Quality Control

Each floor's composite deck had thousands of penetrations for pipe sleeves and hangers, which required exact placement to avoid rework. DPR's VDC team laser-scanned each deck before the Self-Perform Concrete crew poured. From here, strategic partner VConstruct immediately back-checked all scans against the project BIM model for quality control. Once the deck cured, the VDC team went back and laser-scanned again, ensuring all floors met tolerance for flatness.

interior view electrical room where two electricians are installing switchgear

Preventing Supply Chain-related Delays

Due to supply shortages of power transformers and switchgear, lead times from San Diego Gas & Electric (SDG&E) were unknown—creating potential for delays to the project. In response, the project team leveraged its relationships and worked closely with their planner, SDG&E, Gemdale, and trade partners to strategize procurement and make-ready work. The team set and energized all transformers and all plant and equipment before switchgear was set inside the building, avoiding impacts to the schedule.

a DPR project team member shows two trade partner foremen a dig board outside of the project trailer

Phased Turnover of Active Campus

To maintain tenant access to Buildings 1 and 2 during construction of Buildings 3 and 4, the core-and-shell team worked closely with facilities, trade partners, self-perform crews, and the TI project team to coordinate a smoother phasing process. This helped prevent disruptions to occupied spaces as well as create efficiencies for the incoming TI work. Solutions included building a pedestrian bridge from the parking garage to Buildings 1 and 2, allowing office users to safely traverse through the active construction zone.

aerial drone photo showing exterior of two 4-story research buildings and parking garage on the Neurocrine Biosciences Aperture campus
exterior view of two story wellness center with reflection of campus off of glass curtain wall
interior view of second-floor mezzanine fitness area full of exercise machines and floor-to-ceiling glass for natural lighting
interior daytime view of fitness center showing row of treadmills and row of exercise machines
inside view of aerobics room with floor-to-ceiling mirrors and a shelf of exercise equipment
interior view of massage room with two massage chairs and water cooler
interior view of restroom sinks and mirrors with high-end finishes
aerial drone photo showing exterior of two 4-story research buildings and parking garage on the Neurocrine Biosciences Aperture campus
exterior view of two story wellness center with reflection of campus off of glass curtain wall
interior view of second-floor mezzanine fitness area full of exercise machines and floor-to-ceiling glass for natural lighting
interior daytime view of fitness center showing row of treadmills and row of exercise machines
inside view of aerobics room with floor-to-ceiling mirrors and a shelf of exercise equipment
interior view of massage room with two massage chairs and water cooler
interior view of restroom sinks and mirrors with high-end finishes