BioLegend Campus Expansion
BioLegend Campus Expansion | San Diego, CA
Clear communication and innovative problem solving were major factors in the successful delivery of a new biotech campus in San Diego for BioLegend, an award-winning project that completed ahead of schedule and 2% under budget. From a structural steel design approach that saved the owner time and money, to a critical, late-project interior lighting solution, the design and construction team exceeded the owner’s expectations at every juncture.
Challenge
When news broke in mid-2018 that R&D companies were suffering losses related to damages from certain characteristics of LED light fixtures, the BioLegend team knew they faced a critical challenge that would require a quick and effective solution. Already on a fast track schedule, the project needed to finish on time in order to accommodate a long-planned global immunology event that BioLegend was slated to host in May of 2019.
Photo: The project converted an existing 7.5-acre, four-parcel plot of land into an 8-acre biotechnology campus.
California’s Title 24 Code had led to the replacement of most fluorescent light fixtures with LEDs. But with just five months or so left on the project, changing light fixture types would cost anywhere from $450,000 to $1 million and could add anywhere from two to four months in schedule delays.
Challenge
When news broke in mid-2018 that R&D companies were suffering losses related to damages from certain characteristics of LED light fixtures, the BioLegend team knew they faced a critical challenge that would require a quick and effective solution. Already on a fast track schedule, the project needed to finish on time in order to accommodate a long-planned global immunology event that BioLegend was slated to host in May of 2019.
Photo: The project converted an existing 7.5-acre, four-parcel plot of land into an 8-acre biotechnology campus.
California’s Title 24 Code had led to the replacement of most fluorescent light fixtures with LEDs. But with just five months or so left on the project, changing light fixture types would cost anywhere from $450,000 to $1 million and could add anywhere from two to four months in schedule delays.
Solutions
To solve the 11th hour lighting challenge and avoid delays, DPR, Hughes Marino (owner’s representative/construction manager), Bergelectric (electrical contractor), Delawie and BioLegend worked closely together to research and brainstorm options for a lighting fix. Potential solutions that were explored included adding colored lens, applying films to the lights already on site, and testing over a dozen different LED and fluorescent light fixtures. Ultimately, the team uncovered the root cause of the issue and determined that dimming the lights was the best solution. They found a fixture with the appropriate characteristics, thereby avoiding major budget and schedule impacts.
Photo: Potential solutions that were explored included adding colored lens, applying films to the lights already on site, and testing over a dozen different LED and fluorescent light fixtures.
Another innovative project solution that yielded major benefits was the decision to use the patented bolted SidePlate connections for the steel moment frames, eliminating the need for full-penetration welded connections as required in high-seismic regions. These connections reduced joint time in the field from a typical two to four hours for welded joints, to just 30 minutes. The system further saved inspection costs, provided safety advantages, and reduced cost in the amount of steel tonnage required (decreasing the project’s steel design by 58 tons compared to a conventional moment frame design).
Photo: Another innovative project solution that yielded major benefits was the decision to use the patented bolted SidePlate connections for the steel moment frames.
Solutions
To solve the 11th hour lighting challenge and avoid delays, DPR, Hughes Marino (owner’s representative/construction manager), Bergelectric (electrical contractor), Delawie and BioLegend worked closely together to research and brainstorm options for a lighting fix. Potential solutions that were explored included adding colored lens, applying films to the lights already on site, and testing over a dozen different LED and fluorescent light fixtures. Ultimately, the team uncovered the root cause of the issue and determined that dimming the lights was the best solution. They found a fixture with the appropriate characteristics, thereby avoiding major budget and schedule impacts.
Photo: Potential solutions that were explored included adding colored lens, applying films to the lights already on site, and testing over a dozen different LED and fluorescent light fixtures.
Another innovative project solution that yielded major benefits was the decision to use the patented bolted SidePlate connections for the steel moment frames, eliminating the need for full-penetration welded connections as required in high-seismic regions. These connections reduced joint time in the field from a typical two to four hours for welded joints, to just 30 minutes. The system further saved inspection costs, provided safety advantages, and reduced cost in the amount of steel tonnage required (decreasing the project’s steel design by 58 tons compared to a conventional moment frame design).
Photo: Another innovative project solution that yielded major benefits was the decision to use the patented bolted SidePlate connections for the steel moment frames.
Results
The project converted an existing 7.5-acre, four-parcel plot of land into an 8-acre biotechnology campus.
Photo: The project converted an existing 7.5-acre, four-parcel plot of land into an 8-acre biotechnology campus.
The project features a design that encourages collaboration with plenty of natural daylight, expansive views and flexible laboratory spaces.
Photo: The project features a design that encourages collaboration with plenty of natural daylight, expansive views and flexible laboratory spaces.
Additional facility features include lab space, office and amenity space, site improvements, a new seven-story, 700-stall parking garage, a pedestrian bridge, yoga studio and gym, commercial kitchen, 65-ft.-tall structural glass atrium and more.
Photo: Additional facility features include lab space, office and amenity space, site improvements, a new seven-story, 700-stall parking garage, a pedestrian bridge, yoga studio and gym, commercial kitchen, 65-ft.-tall structural glass atrium and more.
Working with San Diego architect Delawie, DPR turned over the BioLegend Campus Expansion project in February 2019 after just 19 months of construction, ahead of schedule and 2% under budget.
Photo: Working with San Diego architect Delawie, DPR turned over the BioLegend Campus Expansion project in February 2019 after just 19 months of construction, ahead of schedule and 2% under budget.
Results
The project converted an existing 7.5-acre, four-parcel plot of land into an 8-acre biotechnology campus.
Photo: The project converted an existing 7.5-acre, four-parcel plot of land into an 8-acre biotechnology campus.
The project features a design that encourages collaboration with plenty of natural daylight, expansive views and flexible laboratory spaces.
Photo: The project features a design that encourages collaboration with plenty of natural daylight, expansive views and flexible laboratory spaces.
Additional facility features include lab space, office and amenity space, site improvements, a new seven-story, 700-stall parking garage, a pedestrian bridge, yoga studio and gym, commercial kitchen, 65-ft.-tall structural glass atrium and more.
Photo: Additional facility features include lab space, office and amenity space, site improvements, a new seven-story, 700-stall parking garage, a pedestrian bridge, yoga studio and gym, commercial kitchen, 65-ft.-tall structural glass atrium and more.
Working with San Diego architect Delawie, DPR turned over the BioLegend Campus Expansion project in February 2019 after just 19 months of construction, ahead of schedule and 2% under budget.
Photo: Working with San Diego architect Delawie, DPR turned over the BioLegend Campus Expansion project in February 2019 after just 19 months of construction, ahead of schedule and 2% under budget.
Awards
California's Best Projects 2019
Engineering News-Record awarded the BioLegend Campus Expansion project its “Best of the Best Projects 2019” award, one of just 20 projects bestowed the honor from a field of 900 highly competitive entries nationwide.
Photo: Working with San Diego architect Delawie, DPR turned over the BioLegend Campus Expansion project in February 2019 after just 19 months of construction.
Award of Excellence
Biolegend Campus was awarded first place in the 2020 San Diego Business Journal “Commercial Real Estate Awards” in the Industrial category.
Photo: The Biolegend campus included a design that encourages collaboration with plenty of natural daylight, expansive views and flexible laboratory spaces.
Awards
California's Best Projects 2019
Engineering News-Record awarded the BioLegend Campus Expansion project its “Best of the Best Projects 2019” award, one of just 20 projects bestowed the honor from a field of 900 highly competitive entries nationwide.
Photo: Working with San Diego architect Delawie, DPR turned over the BioLegend Campus Expansion project in February 2019 after just 19 months of construction.
Award of Excellence
Biolegend Campus was awarded first place in the 2020 San Diego Business Journal “Commercial Real Estate Awards” in the Industrial category.
Photo: The Biolegend campus included a design that encourages collaboration with plenty of natural daylight, expansive views and flexible laboratory spaces.