exterior view of new Kaiser San Marcos medical center with stone-lined patio and glass-and-steel 7-story hospital tower in the background

Bringing Reimagined Care to San Diego's North County

Kaiser Permanente San Marcos Medical Center | San Marcos, California

The new San Marcos Medical Center is a state-of-the-art, 433,000-sq.-ft. hospital addition that includes a HCAI OSHPD-1 patient tower, central utility plant (CUP), and extensive sitework. Built adjacent to the existing multi-specialty San Marcos Medical Offices, the new medical center underscores Kaiser Permanente’s commitment to San Diego's North County.

About the

Project

The seven-story hospital includes 206 beds, eight operating rooms, a 39-bay emergency room, two C-section rooms, an ICU, neo-natal intensive care unit, maternity care, and 204 parking spaces. Infectious disease treatment, cardiology, general surgery, and orthopedics are among the services the new medical center brings to the San Diego region. Designed for expansion, the hospital includes 29,000 sq. ft. of shell space to meet future community needs.

Kaiser’s determination to provide high-quality, affordable care was met with the team’s persistence in working with key trade partners toward the most cost-effective and efficient options. The project finished below budget and two months ahead of schedule. Expedited owner decision-making, target-cost budgeting, detailed forecasting, and iterative feedback removed typical schedule roadblocks. Other strategies included an ambitious teaming process and VDC-led design-assist approach, early procurement of critical-path materials, targeted phasing and permitting, and prefabrication.

external view of the 7 story glass and steel hospital tower at Kaiser San Marcos Medical Center
Certified

LEED Platinum

Green features include reclaimed water use for landscaping and cooling towers, EV charging stations, rideshare and vanpool parking, bike racks, showers for alternative commuters, and drought-tolerant indigenous landscaping. The hospital is also equipped with a first-of-its-kind DC-powered LED lighting system and active chilled beams. Building envelope and glass were selected based on thermal rating, and the glazing type, frit patterns, and sunshades were also optimized for direct sunlight, all to reduce HVAC demand and improve occupant comfort.

The

Challenges

Fast-Track Schedule

The project’s schedule was aggressive for a ground-up, OSHPD-1 hospital tower, spanning four years from start of design to Certificate of Occupancy. Pandemic-related challenges threatened on-time completion, as did existing campus operations, site constraints, and rigorous permitting and inspection processes. From day one, the project team worked closely with the City of San Marcos, HCAI, and Kaiser Permanente to find solutions.

Rigorous Quality Requirements

The process of closing up ceilings and walls was a major effort as trades made their way up the 7-story tower. OSHPD inspections involve finalizing complex MEP work and related support, insulation, and seismic requirements. Also, the team’s ability to hit milestones was affected by labor availability amid market- and pandemic-driven shortages of skilled craft.

Existing Site/Operational Constraints

Building next to four active medical office buildings, our limited site access, parking, and laydown became even more challenging as the pandemic progressed. One major disruption to campus was removing the existing loading dock and relocating the medical offices’ deliveries to the hospital’s new (shared) loading dock. The new loading dock, CUP, and basement required a total excavation of 134,000 cubic yards of dirt and blasting of 77,000 cubic yards of rock.

Doctor talks to nurse at front desk inside of hospital pre- and post-operative care unit that features 45 bays.
hospital upper floor lobby area with people sitting and waiting, reception desk where two people are talking, nurse and doctor walking together past area while talking
exterior view of back side of new Kaiser San Marcos Medical center showing below-grade six-bay loading dock
The

Challenges

Doctor talks to nurse at front desk inside of hospital pre- and post-operative care unit that features 45 bays.

Fast-Track Schedule

The project’s schedule was aggressive for a ground-up, OSHPD-1 hospital tower, spanning four years from start of design to Certificate of Occupancy. Pandemic-related challenges threatened on-time completion, as did existing campus operations, site constraints, and rigorous permitting and inspection processes. From day one, the project team worked closely with the City of San Marcos, HCAI, and Kaiser Permanente to find solutions.

hospital upper floor lobby area with people sitting and waiting, reception desk where two people are talking, nurse and doctor walking together past area while talking

Rigorous Quality Requirements

The process of closing up ceilings and walls was a major effort as trades made their way up the 7-story tower. OSHPD inspections involve finalizing complex MEP work and related support, insulation, and seismic requirements. Also, the team’s ability to hit milestones was affected by labor availability amid market- and pandemic-driven shortages of skilled craft.

exterior view of back side of new Kaiser San Marcos Medical center showing below-grade six-bay loading dock

Existing Site/Operational Constraints

Building next to four active medical office buildings, our limited site access, parking, and laydown became even more challenging as the pandemic progressed. One major disruption to campus was removing the existing loading dock and relocating the medical offices’ deliveries to the hospital’s new (shared) loading dock. The new loading dock, CUP, and basement required a total excavation of 134,000 cubic yards of dirt and blasting of 77,000 cubic yards of rock.

The

Solutions

Design-Assist and “One Model” Approach

The team took an ambitious design-assist and “One Model” approach, bringing on 24 trades as design-assist partners in strategic waves. Designers and detailers shared the same BIM model, and subcontractors created both permit and field drawings simultaneously. When crews showed up on site to begin work, their materials were ready, the budgets were set, and permits were approved.

Divide & Conquer Work/Inspection Zones

Instead of a traditional floor-by-floor approach, the team designated four crews per subcontractor and four respective zones that functioned as “projects within the project.” Scripted work planning within and between these zones reduced downtime and rework. This also helped “dissect” the building on more complicated floors featuring diagnostic and treatment areas or kitchen space. In addition, the team worked closely with key trade partners to prioritize strategic overtime for critical-path trades and provide early access to critical and larger areas leading up to turnover.


Creative Sequencing and Prefabrication

To maintain loading dock access for the occupied campus, the new hospital loading dock and CUP were turned over nine months before the completion of the hospital. The early turnover required detailed coordination and sequencing for deliveries, crane movements, and installation of seven new underground tanks in a constrained space.

The team also elected to prefabricate risk-prone and trade-intensive building components, including medical gas headwalls for patient rooms. These were built on a shared jig by trade partners at the project’s off-site warehouse, hauled two miles to the site, and craned into place. This approach also saved time by increasing quality and consistency, and proved critical to keeping the fast-track schedule.

a hand holds up an ipad with a structural steel 3D model on screen with real life steel structure of the hospital construction project in the background
construction drawing showing overhead view of hospital floor plan with color-coded work and inspection zones of blue, yellow, orange and green
two workers snap a chalk line on a prefabricated medical gas wall being built inside a warehouse
The

Solutions

a hand holds up an ipad with a structural steel 3D model on screen with real life steel structure of the hospital construction project in the background

Design-Assist and “One Model” Approach

The team took an ambitious design-assist and “One Model” approach, bringing on 24 trades as design-assist partners in strategic waves. Designers and detailers shared the same BIM model, and subcontractors created both permit and field drawings simultaneously. When crews showed up on site to begin work, their materials were ready, the budgets were set, and permits were approved.

construction drawing showing overhead view of hospital floor plan with color-coded work and inspection zones of blue, yellow, orange and green

Divide & Conquer Work/Inspection Zones

Instead of a traditional floor-by-floor approach, the team designated four crews per subcontractor and four respective zones that functioned as “projects within the project.” Scripted work planning within and between these zones reduced downtime and rework. This also helped “dissect” the building on more complicated floors featuring diagnostic and treatment areas or kitchen space. In addition, the team worked closely with key trade partners to prioritize strategic overtime for critical-path trades and provide early access to critical and larger areas leading up to turnover.


two workers snap a chalk line on a prefabricated medical gas wall being built inside a warehouse

Creative Sequencing and Prefabrication

To maintain loading dock access for the occupied campus, the new hospital loading dock and CUP were turned over nine months before the completion of the hospital. The early turnover required detailed coordination and sequencing for deliveries, crane movements, and installation of seven new underground tanks in a constrained space.

The team also elected to prefabricate risk-prone and trade-intensive building components, including medical gas headwalls for patient rooms. These were built on a shared jig by trade partners at the project’s off-site warehouse, hauled two miles to the site, and craned into place. This approach also saved time by increasing quality and consistency, and proved critical to keeping the fast-track schedule.

Shared Ownership of

Quality

DPR Quality and VDC professionals, trade partners, and inspectors of record (IORs) owned the project’s QA/QC program together, meeting daily on site to review inspections for the day and week ahead, and prioritizing certain trades in the event of a time crunch. Also, with full-time QC representatives on both sides, DPR and subcontractors performed in-house inspections and made corrections prior to calling for formal inspections.

VDC involvement factored heavily into successful quality outcomes. In addition to using the BIM model as a single source of truth, DPR also used laser scanning and daily 360° photos to record progress, assess clashes, and document as-built conditions. These strategies reduced rework at every stage, from catching out-of-place embeds ahead of deck pours to fixing punch-list items before turnover.

four project team members in safety vests examine a 3D BIM model on a flat screen monitor inside a construction jobsite trailer
interior view of hallway on 4th floor of hospital lined with window wall showing 7-story patient tower in background

Kaiser opens San Marcos Medical Center, adding 206 new beds and bringing 1,100 jobs to the area. 

Read more

interior view of hospital cafe shows high ceilings, glass curtain wall, and mountain/ocean inspired mosaic on wall above dining area
The design harnesses the region’s unique sites by including features such as a custom tile mosaic in the café dedicated to Lake San Marcos, one of the region’s “Points of Discovery.”
The main entry rotunda’s hosts a welcoming lobby with custom art, unique design features, and natural light.
The main entry rotunda’s design harnesses natural light in a bright, welcoming lobby with custom art and unique design features such as the rock garden inspired by Lake San Marcos under the grand stair.
nurse stands in a new hospital patient room that features prefabricated headwalls and footwalls.
The headwalls and footwalls in med surg and ICU rooms were prefabricated at the project’s off-site warehouse by the construction trades. This increased consistency and production on each floor. Footwalls were designed for the TV to be recessed and include a camera for patient viewing, allowing for telehealth.
Hospital NICU interior showing nurse next to infant medical bed.
The NICU is built out to support eight bassinets in four room types. These are arranged as a 4-bed, 2-bed, 1-private, and 1-infection-isolation room, as well as 8,000 sq. ft. of shell space for future NICU expansion.
Doctor talks to nurse at front desk inside of hospital pre- and post-operative care unit that features 45 bays.
The pre- and post-operative care unit consists of 45 bays to support eight operating rooms and two IR rooms, as well as 2,300 sq. ft. of available shell space for future ORs and/or IRs.
Interior view of a completed interventional radiology (IR) room, where nurse is logging into operate equipment.
Two interventional radiology (IR) rooms are located on the second floor in the same suite as the operating rooms (ORs). Canon supplied imaging equipment along with Guardian Ceiling systems in both IRs and ORs.
interior view of hospital cafe shows high ceilings, glass curtain wall, and mountain/ocean inspired mosaic on wall above dining area
The design harnesses the region’s unique sites by including features such as a custom tile mosaic in the café dedicated to Lake San Marcos, one of the region’s “Points of Discovery.”
The main entry rotunda’s hosts a welcoming lobby with custom art, unique design features, and natural light.
The main entry rotunda’s design harnesses natural light in a bright, welcoming lobby with custom art and unique design features such as the rock garden inspired by Lake San Marcos under the grand stair.
nurse stands in a new hospital patient room that features prefabricated headwalls and footwalls.
The headwalls and footwalls in med surg and ICU rooms were prefabricated at the project’s off-site warehouse by the construction trades. This increased consistency and production on each floor. Footwalls were designed for the TV to be recessed and include a camera for patient viewing, allowing for telehealth.
Hospital NICU interior showing nurse next to infant medical bed.
The NICU is built out to support eight bassinets in four room types. These are arranged as a 4-bed, 2-bed, 1-private, and 1-infection-isolation room, as well as 8,000 sq. ft. of shell space for future NICU expansion.
Doctor talks to nurse at front desk inside of hospital pre- and post-operative care unit that features 45 bays.
The pre- and post-operative care unit consists of 45 bays to support eight operating rooms and two IR rooms, as well as 2,300 sq. ft. of available shell space for future ORs and/or IRs.
Interior view of a completed interventional radiology (IR) room, where nurse is logging into operate equipment.
Two interventional radiology (IR) rooms are located on the second floor in the same suite as the operating rooms (ORs). Canon supplied imaging equipment along with Guardian Ceiling systems in both IRs and ORs.
We think you'll like this, too.