Aerial shot of project

KPMG Lakehouse

KPMG Lakehouse | Orlando, Florida

A shared commitment to continuous learning and development, teamwork and quality set the tone for DPR’s construction of the largest single capital project that global professional services firm KPMG had ever undertaken: the 767,000-sq.-ft. KPMG Lakehouse corporate training facility.

Located on a 55-acre site within Orlando’s Lake Nona Sports & Performance District, the Lakehouse boasts 350,000-sq.-ft. of training and classroom space, 800 guest rooms and 15,000-sq.-ft. of amenity space, including fitness and outdoor recreation areas. The environmentally friendly, LEED Silver certified facility also features a heritage center which highlights KPMG’s rich history and culture as the fastest growing Big Four professional services firms in the U.S.

Aerial shot of project

Teamwork and Prefabrication

At the earliest stage of the project, DPR participated in a high-performing team building session with KPMG and Gensler. Together they created a mission to make this a project where everyone — from trade partners to design and construction team members — wanted to come to work.

DPR used prefabrication for key portions of work, including SurePods factory-built bathrooms, the exterior curtain wall system, as well as many mechanical, electrical and plumbing components. Almost 10% of total construction volume was self-performed by DPR with its own crews. This combination off-site prefabrication and self-perform work resulted in improved quality, schedule and project safety.

The

Challenges

Delivering the largest capital project that KPMG had ever undertaken was no small challenge. The project’s sheer size, combined with a 24-month construction schedule, demanded a deep range of expertise to optimize value, schedule and delivery of this state-of-the-art facility.

Photo: Delivering the largest capital project that KPMG had ever undertaken was no small challenge.

Construction site in progress
The

Challenges

Construction site in progress

Delivering the largest capital project that KPMG had ever undertaken was no small challenge. The project’s sheer size, combined with a 24-month construction schedule, demanded a deep range of expertise to optimize value, schedule and delivery of this state-of-the-art facility.

Photo: Delivering the largest capital project that KPMG had ever undertaken was no small challenge.

The

Solutions

By prefabricating the bathrooms, the exterior curtain wall system, and many mechanical, electrical and plumbing components, DPR decreased the number of on-site craft workers needed and effectively shifted fabrication to a controlled off-site environment.

Photo: By prefabricating the bathrooms, the exterior curtain wall system, and many mechanical, electrical and plumbing components, DPR decreased the number of on-site craft workers needed and effectively shifted fabrication to a controlled off-site environment.

The project team engaged SurePods early to prefabricate and deliver 800 fully finished bathrooms to the jobsite. The ability to control fabrication, just-in-time delivery to the jobsite and the installation schedule were major benefits. In addition to shaving weeks off the schedule, the factory-built bathrooms resulted in predictable results with pre-punch completed in the factory prior to setting and delivering.

Photo: The ability to control fabrication, just-in-time delivery to the jobsite and the installation schedule were major benefits.

The unitized curtainwall system was delivered to the project ready to rig set. All 2,600 units were picked directly from the truck and set in place, allowing the project to get “dried-in” within six months. Many of the building’s mechanical, electrical and plumbing components were also prefabricated.

Real-time, in-the-field innovations by DPR’s self-perform team was another key solution that benefitted project quality and improved onsite safety. In just one example, the in-house drywall team used their expertise to find alternate UL assembly to save needed space within the building shafts.

Photo: Real-time, in-the-field innovations by DPR’s self-perform team was another key solution that benefitted project quality and improved onsite safety.

The design and construction team also delivered numerous energy-efficient solutions to the environmentally friendly, LEED Silver certified facility, which is estimated to use 28% less energy than similar facilities of its size thanks to the optimization of mechanical systems and integrated technologies. Powered by 100% renewable energy, the green features include natural daylighting illuminating 90% of interior spaces; and low-flow plumbing fixtures to reduce water consumption by 30% across the property.

Photo: Powered by 100% renewable energy, the green features include natural daylighting illuminating 90% of interior spaces; and low-flow plumbing fixtures to reduce water consumption by 30% across the property.

By working as part of a cohesive, high-performing team and employing solutions from prefabrication and laser scanning to self-perform work, DPR successfully delivered KPMG’s largest project ever a full two months ahead of schedule in late 2019.

Prefabricated bathroom
Progress shot of construction site.
Exterior building construction in progress with use of a crane
Aerial shot of the project
The

Solutions

Prefabricated bathroom

By prefabricating the bathrooms, the exterior curtain wall system, and many mechanical, electrical and plumbing components, DPR decreased the number of on-site craft workers needed and effectively shifted fabrication to a controlled off-site environment.

Photo: By prefabricating the bathrooms, the exterior curtain wall system, and many mechanical, electrical and plumbing components, DPR decreased the number of on-site craft workers needed and effectively shifted fabrication to a controlled off-site environment.

Progress shot of construction site.

The project team engaged SurePods early to prefabricate and deliver 800 fully finished bathrooms to the jobsite. The ability to control fabrication, just-in-time delivery to the jobsite and the installation schedule were major benefits. In addition to shaving weeks off the schedule, the factory-built bathrooms resulted in predictable results with pre-punch completed in the factory prior to setting and delivering.

Photo: The ability to control fabrication, just-in-time delivery to the jobsite and the installation schedule were major benefits.

Exterior building construction in progress with use of a crane

The unitized curtainwall system was delivered to the project ready to rig set. All 2,600 units were picked directly from the truck and set in place, allowing the project to get “dried-in” within six months. Many of the building’s mechanical, electrical and plumbing components were also prefabricated.

Real-time, in-the-field innovations by DPR’s self-perform team was another key solution that benefitted project quality and improved onsite safety. In just one example, the in-house drywall team used their expertise to find alternate UL assembly to save needed space within the building shafts.

Photo: Real-time, in-the-field innovations by DPR’s self-perform team was another key solution that benefitted project quality and improved onsite safety.

Aerial shot of the project

The design and construction team also delivered numerous energy-efficient solutions to the environmentally friendly, LEED Silver certified facility, which is estimated to use 28% less energy than similar facilities of its size thanks to the optimization of mechanical systems and integrated technologies. Powered by 100% renewable energy, the green features include natural daylighting illuminating 90% of interior spaces; and low-flow plumbing fixtures to reduce water consumption by 30% across the property.

Photo: Powered by 100% renewable energy, the green features include natural daylighting illuminating 90% of interior spaces; and low-flow plumbing fixtures to reduce water consumption by 30% across the property.

By working as part of a cohesive, high-performing team and employing solutions from prefabrication and laser scanning to self-perform work, DPR successfully delivered KPMG’s largest project ever a full two months ahead of schedule in late 2019.

The

Results

The KPMG Lakehouse project received the Best Green Project award in Orlando Business Journal’s 2019 Structures Awards program.

Photo: The KPMG Lakehouse project received the Best Green Project award in Orlando Business Journal’s 2019 Structures Awards program.

building exterior shot
The

Results

building exterior shot

The KPMG Lakehouse project received the Best Green Project award in Orlando Business Journal’s 2019 Structures Awards program.

Photo: The KPMG Lakehouse project received the Best Green Project award in Orlando Business Journal’s 2019 Structures Awards program.

DPR’s broad experience and cutting-edge approach to corporate office, campus and hospitality projects dovetailed exceptionally well with the nature of our campus. Their strong working relationship with Gensler helped ensure that our design vision was executed with the highest quality and greatest attention to detail.

Bill Flemming

Head of Construction, KPMG

exterior of building
KPMG| Lake House | Orlando, FL
sitting area with large windows
lobby area with staircase
lobby area lit up with colorful lights

A shared commitment to continuous learning and development, teamwork and quality set the tone for DPR’s construction of the largest single capital project that global professional services firm KPMG had ever undertaken: the 767,000-sq.-ft. KPMG Lakehouse corporate training facility.

Located on a 55-acre site within Orlando’s Lake Nona Sports & Performance District, the Lakehouse boasts 350,000-sq.-ft. of training and classroom space, 800 guest rooms and 15,000-sq.-ft. of amenity space, including fitness and outdoor recreation areas

The environmentally friendly, LEED Silver certified facility also features a heritage center which highlights KPMG’s rich history and culture as the fastest growing Big Four professional services firms in the U.S.

DPR used prefabrication for key portions of work, including SurePods factory-built bathrooms, the exterior curtain wall system, as well as many mechanical, electrical and plumbing components.

exterior of building
KPMG| Lake House | Orlando, FL

A shared commitment to continuous learning and development, teamwork and quality set the tone for DPR’s construction of the largest single capital project that global professional services firm KPMG had ever undertaken: the 767,000-sq.-ft. KPMG Lakehouse corporate training facility.

sitting area with large windows

Located on a 55-acre site within Orlando’s Lake Nona Sports & Performance District, the Lakehouse boasts 350,000-sq.-ft. of training and classroom space, 800 guest rooms and 15,000-sq.-ft. of amenity space, including fitness and outdoor recreation areas

lobby area with staircase

The environmentally friendly, LEED Silver certified facility also features a heritage center which highlights KPMG’s rich history and culture as the fastest growing Big Four professional services firms in the U.S.

lobby area lit up with colorful lights

DPR used prefabrication for key portions of work, including SurePods factory-built bathrooms, the exterior curtain wall system, as well as many mechanical, electrical and plumbing components.