Lab working working with beef cell machines

SCiFi Foods

SCiFi Foods | San Leandro, California

DPR Construction worked with SCiFi Foods, a company that cultivates meat from cells, in building a pilot lab and working space in San Leandro, California to support its Bay Area operations.

Partners

About the

Project

The project included a 4,000 sq. ft lab space on the second floor of a two-story warehouse with ISO 7 and ISO 8 clean rooms for inoculation, manufacturing, harvesting, and quality control along with supporting offices, and materials management. The sub-scale pilot plant was designed to support the scale-up activities for SCiFi Foods to develop cultured beef products from small-scale research quantities to 500L bioreactor quantities.

SCiFi Foods internal rack of lab coats for all employees

Our First Commercial-Scale Production of Cultivated Beef

Design-to-Build

This design-to-build project was delivered in 7 months with the target budget set at the beginning of the project. The combination of the client-provided program and process information, material and personnel flows, and DPR's design-to-build expertise helped establish a clear plan from the start. DPR’s project team onboarded the architect and MEPF (Mechanical, Electrical, Plumbing, & Fire Protection) trade partners early, and created the integrated team to develop a design that met the owner's target budget and then documented for permitting, bidding, buyout, construction and record purposes.

Not only was this project completed on time and on budget but SCiFi Foods is now the only company in the world with beef cell lines that grow in single-cell suspension, enabling them to scale production of cultivated beef quickly and affordably.

Open office space with a view into lab station

Self-Perform Work

Our Self Perform Work (SPW) team performed all drywall, ceilings, doors, frames, and hardware on this project. With the project delivery schedule being a prominent concern for the client, we were able to shave off a significant amount of time by identifying the preexisting conditions of the building and support the architectural design and documentation efforts with constructive input meeting quality, schedule and cost goals.

Two employees looking into a window that see into a lab facility.
Open office space with a view into lab station

Design-to-Build

This design-to-build project was delivered in 7 months with the target budget set at the beginning of the project. The combination of the client-provided program and process information, material and personnel flows, and DPR's design-to-build expertise helped establish a clear plan from the start. DPR’s project team onboarded the architect and MEPF (Mechanical, Electrical, Plumbing, & Fire Protection) trade partners early, and created the integrated team to develop a design that met the owner's target budget and then documented for permitting, bidding, buyout, construction and record purposes.

Not only was this project completed on time and on budget but SCiFi Foods is now the only company in the world with beef cell lines that grow in single-cell suspension, enabling them to scale production of cultivated beef quickly and affordably.

Two employees looking into a window that see into a lab facility.

Self-Perform Work

Our Self Perform Work (SPW) team performed all drywall, ceilings, doors, frames, and hardware on this project. With the project delivery schedule being a prominent concern for the client, we were able to shave off a significant amount of time by identifying the preexisting conditions of the building and support the architectural design and documentation efforts with constructive input meeting quality, schedule and cost goals.