UCSF Medical Center at Mission Bay
UCSF Medical Center at Mission Bay | San Francisco, California
DPR collaborated with the University of California at San Francisco (UCSF), Stantec Architecture, Cambridge CM and 17 subcontractors at the Integrated Center for Design and Construction (ICDC) to deliver the ground-up, $1.52 billion UCSF Medical Center at Mission Bay. Marking the culmination of over a decade of planning, design and construction, the 289-bed, six-story, 878,000-square-foot facility opened for patients on February 1, 2015.
Facility
The integrated hospital complex includes:
- The 183-bed UCSF Benioff Children's Hospital at Mission Bay with an urgent care/emergency department, pediatric primary care and specialty outpatient care;
- The UCSF Betty Irene Moore Women's Hospital with 36 beds, cancer care, specialty surgery and birth center;
- UCSF Bakar Cancer Hospital, part of the Helen Diller Family Comprehensive Cancer Center, that houses 70 beds, and offers inpatient and outpatient surgery for cancer specialties;
- A 207, 400-square-foot outpatient building; and
- A 36,000- square-foot energy center, helipad, parking and support services
More than 250 architects, engineers and contractors co-located in the ICDC on the 14-acre project site beginning early in the design phase, where they focused on building a high-performing, integrated team that adhered to the motto of, “first, doing what’s best for the project.” By bringing key subcontractors on board nearly two years before construction began, the project team was able to virtually build the medical center to a high level of detail prior to constructing it in the field.
The LEED Gold-certified medical complex was built with sustainability in mind, and includes 16 individual gardens that total 4.3 acres of green space. Delivered eight days ahead of schedule despite implementing nearly $55 million in changes, the UCSF Medical Center at Mission Bay passed the California Department of Public Health’s licensing inspections with “no deficiencies” – unprecedented among new California hospitals. The result is a world-class facility completed early and built with the highest level of quality.
Project Process
Challenges
Comprehensive Project Delivery in an Urban Area
Delivering a comprehensive, new OSHPD-regulated hospital in a largely populated urban area, and over a multi-year period, presented largescale challenges for the design and construction team. Effectively managing change and producing a consistent, predictable result was an overriding goal for the high-performing team.
Change in Scope
One of the biggest challenges occurred well into construction. It was a major scope change that required reprogramming of the six-story, 200,000-square-foot outpatient building. Totaling $55 million in changes alone and encompassing a rework of the entire building layout, the reprogramming was needed to accommodate how healthcare services, patient needs and equipment had evolved from the start of the project. DPR was challenged to deliver the changes without impacting the budget or schedule, while maintaining quality standards.
Challenges
Comprehensive Project Delivery in an Urban Area
Delivering a comprehensive, new OSHPD-regulated hospital in a largely populated urban area, and over a multi-year period, presented largescale challenges for the design and construction team. Effectively managing change and producing a consistent, predictable result was an overriding goal for the high-performing team.
Change in Scope
One of the biggest challenges occurred well into construction. It was a major scope change that required reprogramming of the six-story, 200,000-square-foot outpatient building. Totaling $55 million in changes alone and encompassing a rework of the entire building layout, the reprogramming was needed to accommodate how healthcare services, patient needs and equipment had evolved from the start of the project. DPR was challenged to deliver the changes without impacting the budget or schedule, while maintaining quality standards.
Managing Expectations
Solutions
Procuring Key Trades Early
The project team was able to procure key trades early on for modeling and coordination during preconstruction. This allowed the custom details for equipment support to be engineered and crafted in time to make the initial permit set, thus minimizing any permit-related changes orders during construction and, consequently, reducing any schedule impacts.
BIM Coordination
The project’s high degree of BIM coordination was another key solution, encompassing everything from model-based estimating to MEP coordination, 4D sequencing, constructability analysis, total station integration, site logistics planning, and more. By virtually building the medical center in an intricately detailed model prior to construction, the team could uncover any problems prior to execution in the field, where changes became much more costly. BIM removed uncertainty from the project schedule, saved time and reduced waste.
An Integrated Team
An integrated team was a key driver behind the successful completion of this project. Together, they defined engagement and scope, set expectations, solidified the project vision, and co-located within the ICDC beginning early in the design phase to further encourage creative problem solving and decision-making as challenges arose.
Collaboration and Creative Problem Solving
The project team collectively developed formalized processes to encourage a working environment conducive to collaboration and creative problem solving, resolving issues and making decisions quickly, dealing with changes efficiently and effectively, and devising a needs-based assessment strategy.
Needs-based Assessment Strategy
Due to their needs-based assessment strategy and effective processes, any large-scale changes were approached as if they were an entirely new project build. Confronted with the challenge of revamping the entire layout of the building after construction was already underway, they quickly created a new team and a new schedule, while retaining the same behaviors, processes and tools proven to be successful thus far. The result: the outpatient building project team revised 18 months of design decisions for the building in a matter of weeks.
Solutions
Procuring Key Trades Early
The project team was able to procure key trades early on for modeling and coordination during preconstruction. This allowed the custom details for equipment support to be engineered and crafted in time to make the initial permit set, thus minimizing any permit-related changes orders during construction and, consequently, reducing any schedule impacts.
BIM Coordination
The project’s high degree of BIM coordination was another key solution, encompassing everything from model-based estimating to MEP coordination, 4D sequencing, constructability analysis, total station integration, site logistics planning, and more. By virtually building the medical center in an intricately detailed model prior to construction, the team could uncover any problems prior to execution in the field, where changes became much more costly. BIM removed uncertainty from the project schedule, saved time and reduced waste.
An Integrated Team
An integrated team was a key driver behind the successful completion of this project. Together, they defined engagement and scope, set expectations, solidified the project vision, and co-located within the ICDC beginning early in the design phase to further encourage creative problem solving and decision-making as challenges arose.
Collaboration and Creative Problem Solving
The project team collectively developed formalized processes to encourage a working environment conducive to collaboration and creative problem solving, resolving issues and making decisions quickly, dealing with changes efficiently and effectively, and devising a needs-based assessment strategy.
Needs-based Assessment Strategy
Due to their needs-based assessment strategy and effective processes, any large-scale changes were approached as if they were an entirely new project build. Confronted with the challenge of revamping the entire layout of the building after construction was already underway, they quickly created a new team and a new schedule, while retaining the same behaviors, processes and tools proven to be successful thus far. The result: the outpatient building project team revised 18 months of design decisions for the building in a matter of weeks.
Delivery
Results
The UCSF Medical Center at Mission Bay was completed eight days ahead of schedule despite the $55 million in changes implemented throughout its multi-year design and construction process. The team made those changes without impacting the budget or schedule, while improving the overall quality of the facility.
Ranked as one of the greenest urban hospitals in the nation, the UCSF Medical Center at Mission Bay received LEED Gold certification prior to occupancy. Its 4.3 acres of green space includes over an acre of rooftop gardens to help reduce storm water runoff. The complex delivers 100 percent outdoor air, rather than re-circulated, to every space.
The project has received multiple awards and recognition for excellence, including the ENR California Best Healthcare Project – 2015, ENR Best Healthcare Project in the nation – 2015, and ASHE Vista New Construction Award.
Results
The UCSF Medical Center at Mission Bay was completed eight days ahead of schedule despite the $55 million in changes implemented throughout its multi-year design and construction process. The team made those changes without impacting the budget or schedule, while improving the overall quality of the facility.
Ranked as one of the greenest urban hospitals in the nation, the UCSF Medical Center at Mission Bay received LEED Gold certification prior to occupancy. Its 4.3 acres of green space includes over an acre of rooftop gardens to help reduce storm water runoff. The complex delivers 100 percent outdoor air, rather than re-circulated, to every space.
The project has received multiple awards and recognition for excellence, including the ENR California Best Healthcare Project – 2015, ENR Best Healthcare Project in the nation – 2015, and ASHE Vista New Construction Award.
Summary
The successful delivery of the UCSF Medical Center at Mission Bay project is a testament to a high-performing team that worked together to effectively manage change, while producing a top-quality project that met or exceeded client expectations, according to J. Stuart Eckblad, executive eirector of Major Capital Projects for UCSF Medical Center. “By embracing and planning for change on a seven-, eight-year project, change is inevitable,” he said. “One of the things that our team is really proud of is that we organized from the beginning with a process for managing change to ensure the best outcomes for the project.”
BIM Features
- Proposal
- Quantity Take-off
- Model Based Estimating
- Self Perform Work Detailing
- Self Perform Work Tracking
- MEP Coordination
- 4D Sequencing
- Constructability Analysis
- Total Station Integration
- Site Logistics Planning
Green Features
One of the greenest urban hospitals in the nation, the UCSF Medical Center at Mission Bay received LEED Gold certification prior to occupancy. The complex features 16 individual gardens totaling 4.3 acres of green space, which includes over an acre of rooftop gardens to help reduce storm water runoff. The complex delivers 100 percent outdoor air, rather than re-circulated, to every space.